SB 35 and SB 423 vs. the New CEQA Infill Exemption (AB 130): Which Fast Track Fits Your LA Project?

With California’s evolving land-use laws, LA developers don’t have to tackle entitlements the old way. Here’s a breakdown of SB 35/423 and the new AB 130 CEQA exemption and how to choose the right fast track for your project. 

Why LA Developers Have Multiple Fast-Track Approval Options

Housing projects in LA used to face two requirements: discretionary approval and CEQA environmental review. Now, California gives developers several ways around one or both steps.

Two routes get the most attention. The first is SB 35, which SB 423 extended and expanded. It skips discretionary review altogether. The second is the new CEQA infill exemption in AB 130, which skips environmental review but not necessarily the rest of the local process.

CEQA stands for the California Environmental Quality Act. It requires public agencies to study the environmental effects of a project before greenlighting it.

What Is SB 35 and How Did SB 423 Change It?

SB 35 passed in 2017. It forces cities that are behind on their housing targets to approve qualifying projects quickly and without public hearings. SB 423 extended the law to 2036, added coastal-zone applicability, and revised the labor standards.

How Streamlined Ministerial Approval Works

Ministerial approval means the city checks your project against objective standards. Officials cannot exercise discretion, hold public hearings, or request changes outside written zoning rules. If you meet the criteria, your permit is granted.

State law imposes firm deadlines: 60 to 90 days for cities to flag non-compliance and 90 to 180 days for final approval, based on project scale.

And because this process is ministerial, it falls outside CEQA. You get full environmental clearance without an environmental study.

SB 423 Eligibility Requirements for Housing Projects

SB 35 fast-tracking only applies in cities that are behind on their state housing goals (known as RHNA goals). The state housing department publishes a list showing which cities qualify and what percentage of affordable housing a developer must include to qualify.

Basic requirements:

  • A project with two or more units built on land zoned for housing
  • Full compliance with the city’s objective rules
  • Protecting existing housing (no tearing down tenant-occupied or rent-controlled units)
  • Building outside hazardous areas, like flood zones, high fire areas, wetlands, or earthquake fault zones

SB 423 expanded eligibility into coastal areas, as long as the site is zoned for multi-family housing and free from environmental or safety hazards. 

Affordability and Prevailing Wage Rules

SB 35 sets two levels for required affordable units, depending on the city’s housing lag:

  • 10% affordable units if the city is missing its targets for middle-to-higher-income housing
  • 50% affordable units if the city is missing its targets for lower-income housing

SB 423 tightened these rules for the 10% category. For rental properties, those affordable units must now serve lower-income households earning up to 50% of the Area Median Income (AMI), down from the previous 80% limit.

Labor standards scale based on overall project size:

  • 10 or fewer units are exempt from prevailing wage and benefit mandates (if privately funded).
  • 11 to 49 units trigger prevailing wage, apprenticeship, and healthcare requirements.
  • 50+ units require additional mandatory expenditures for apprenticeships and healthcare coverage.

What Is the AB 130 CEQA Infill Exemption?

AB 130 (or CA AB130), a budget trailer bill, took effect June 30, 2025. It created a new statutory CEQA exemption for urban infill housing, codified as Public Resources Code section 21080.66.

Note that this is a CEQA exemption only. You still go through your city’s normal process, such as design review.

Which Infill Sites Qualify Under AB 130

The site has to be in an incorporated city or a Census-defined urban area, and it has to be truly infill. That means it was previously developed with an urban use, or most of its perimeter is already developed.

The project has to be a housing development project. That includes residential-only buildings, mixed-use projects (if two-thirds of the area is residential), transitional housing, and farmworker housing. 

Zoning, Density, and Project Size Requirements

To qualify, your project must:

  • Align with the general plan and zoning (after density bonus waivers and concessions).
  • Meet at least half the housing element’s minimum (e.g., 15 units/acre where the target is 30).
  • Not demolish a historic structure
  • Satisfy standard site safety exclusions (avoiding flood risk zones, wetlands, and fire hazard areas).

On size, the exemption covers sites up to 20 acres (or up to 4 acres for builder’s remedy projects under SB 158). 

How AB 130 Differs From the Class 32 CEQA Exemption

If you work in real estate, you probably know Class 32, the standard CEQA exemption used for years to build on city land.

The new AB 130 law works similarly, but with two major advantages:

  • AB 130 is written directly into state law and immune to legal challenges. Class 32 can be overturned in court if opponents cite “unusual circumstances” on your property (like a traffic issue or wildlife). 
  • Class 32 is capped at 5 acres. AB 130 covers sites up to 20 acres.

Tribal Consultation and Approval Timelines

The city must also consult with local Native American tribes:

  • Notification: Notify relevant tribes within 14 days after your application is complete.
  • Request Window: Allow tribes 60 days to request a formal consultation.
  • Consultation: Finish consultation within 45 days, extendable by 15 days.
  • Requirements: The city may add conditions to your permit, such as paying for a tribal monitor on-site during construction.

SB 35 and SB 423 vs. AB 130: Key Differences

Here’s a quick comparison:

SB 35 / SB 423 AB 130 
What you getMinisterial approval (no hearing, no CEQA)CEQA exemption only
Where it worksOnly in cities behind on state housing targetsAny qualifying urban infill site
Affordability 10% or 50%, by HCD tier None required (100% affordable projects pay prevailing wage) 
Site sizeNo set cap, but site exclusions apply Up to 20 acres (4 acres for builder’s remedy) 
ZoningMust meet objective standards Must be consistent with plan and zoning (after density bonus) 
Labor rulesPrevailing wage over 10 units, plus more at 50+ None up to 85 ft in most places; SB 35 standards above 85 ft 
Sunset January 1, 2036 None

Eligibility and Site Requirements

SB 35 depends on your city’s housing record, which can change from year to year. AB 130 depends on your site and design. That makes AB 130 more predictable but also more specific about density and infill. 

CEQA Review and Approval Processes

SB 35 skips discretionary approval. AB 130 skips environmental review. That said, AB 130 does not bypass local zoning. If you need a conditional use permit or zone variance, you still have to get standard city approval. 

Affordability, Labor Standards, and Other Obligations

SB 35 trades speed for affordable units and labor costs. AB 130 doesn’t require affordable housing, and for buildings up to 85 feet, it generally doesn’t impose prevailing wage, except for certain projects in San Francisco. Above 85 feet, the SB 35 construction labor standards apply.  

Which Fast-Track Pathway Fits Your Project?

It depends on the facts of the development:

When SB 423 May Be the Better Fit

  • You already plan on-site affordable units.
  • Your project fits the objective standards cleanly.
  • You want to avoid a hearing and discretionary conditions.
  • You can absorb the labor costs.

When AB 130 May Be the Better Fit

  • You’re building market-rate or mixed-income housing.
  • Your city isn’t subject to SB 35, or the 50 percent tier is out of reach.
  • You have a larger site.
  • You can accept the normal local approval process in exchange for no environmental study.

Pairing a Fast-Track Pathway With the California Density Bonus Law

California density bonus law and these pathways often work together. For AB 130, consistency with zoning is measured after waivers and concessions, so a bonus can help you qualify.

SB 35 projects can use it as well. Just run the combined math early, because stacking benefits changes your unit count and affordability mix. 

How These Laws Apply in the City of Los Angeles

State law establishes the main eligibility rules, but local procedures and site conditions still apply:

How LA’s Housing Element Progress Affects SB 423

L.A. has a certified housing plan but hasn’t issued enough low-income housing permits. Developers can use SB 423 to fast-track projects by setting aside at least 10% of units for very low-income residents.

ED 1 and LA’s Affordable Housing Streamlining Ordinance

For 100 percent affordable projects, ED 1 is the other path to know. Now permanent under city ordinance, it allows qualifying 100% affordable housing developments to skip discretionary hearings and CEQA requirements. Single-family zones are excluded.

Coastal Zone, Historic Resources, and Other Site Exclusions

Coastal areas, hillsides in high fire zones, flood zones, and listed historic buildings all need a careful look under both SB 35 and AB 130. A coastal zone project may qualify under SB 423 but not under AB 130, or the reverse, depending on zoning and the local coastal program. 

Common Mistakes That Can Disqualify a Project From Streamlined Approval

Avoid:

  • Assuming urban location is enough: Both pathways have detailed eligibility conditions.
  • Ignoring density: Too little density fails AB 130. 
  • Underestimating labor costs: These obligations can materially affect project feasibility.
  • Misreading a CEQA exemption: Exemption from environmental review does not eliminate zoning, building, or other applicable legal requirements.
  • Skipping tribal consultation: AB 130’s consultation process should be built into the project schedule.
  • Treating local programs as interchangeable: ED 1, SB 423, AB 130, and Class 32 have different legal foundations and requirements.
  • Waiting until filing to check exclusions: Review environmental constraints, historic resources, and existing housing conditions early.

How Pattern Helps LA Projects Navigate Entitlements and Approvals

Choosing between SB 35 and AB 130 means reading statutes, site maps, and city practice together. Pattern works on entitlements and approvals for LA housing projects and can help you test your site against each pathway before you commit. 

FAQs

Is SB 35 Still in Effect?

Yes. SB 423 extended the streamlined ministerial approval process to January 1, 2036.

Does AB 130 Require Affordable Housing?

No. The exemption doesn’t require affordable housing. The exception is labor. Projects that are 100 percent affordable to lower-income households must pay prevailing wages. 

Is AB 130 Retroactive?

It took effect in 2025 and applies to active or new projects that haven’t been approved yet. It won’t reopen projects that were already finalized, but it does include special transition rules for pending applications, particularly for notifying local tribes.

Does AB 130 Require Tribal Consultation?

Yes. The exemption includes a special consultation process with affiliated tribes. 

What Is the CEQA Near-Miss Exemption?

If your project meets every criterion for an exemption but one, SB 131 limits CEQA review to that single issue. That can rescue a project that falls just outside AB 130 or Class 32.

Need assistance with land use, planning, development or permitting?